Code: A-31
Subject: INDUSTRIAL ENGINEERING
Time: 3 Hours
Max. Marks: 100
NOTE: There are 11 Questions in all.  
  • Question 1 is compulsory and carries 16 marks. Answer to Q. 1. must be written in the space provided for it in the answer book supplied and nowhere else.
  • Answer any THREE Questions each from Part I and Part II. Each of these questions carries 14 marks.
  • Any required data not explicitly given, may be suitably assumed and stated.

Q.1 Choose the correct or best alternative in the following: (2x8)
     
a.
The symbol in process charts is used for  
  (A) Operation.       (B) Inspection.
(C) Delay.             (D) Storage.
 
     
b.
The stop watch used in time study has a least count equal to  
  (A) 0.001 hr.          (B) 0.01 min.
(C) 0.1 s.                (D) 1 s.

 
     
c.
The following is the advantage of process layout :  
  (A) Reduced material handling.
(B) Less capital investment.
(C) Smooth flow of materials.
(D) Less floor area occupied by the material in transit and for temporary storages.
 
     
d.
The following is not the principle of material handling :  
  (A) Reduce the handling of material.
(B) Use unit loads.
(C) Move materials at high speeds.
(D) Use handling equipment below its capacity.
 
     
e.
In a PERT model an activity has the following time estimates :
Pessimistic time = 16 days.
Most likely time = 8 days.
Optimistic time = 4 days.
The expected time estimate to carry out the activity is
 
  (A)   days (B)  days  
  (C)  days (D) days  
     
1