| Code: A-31 |
Subject: INDUSTRIAL ENGINEERING
|
||
| Time: 3 Hours |
Max. Marks: 100
|
||
| NOTE: There are 11 Questions in all. | |||
|
|||
| Q.1 | Choose the correct or best alternative in the following: | (2x8) | |
|
a.
|
The symbol |
||
| (A) Operation. (B)
Inspection. (C) Delay. (D) Storage. |
|||
|
b.
|
The stop watch used in time study has a least count equal to | ||
| (A) 0.001 hr. (B)
0.01 min. (C) 0.1 s. (D) 1 s. |
|||
|
c.
|
The following is the advantage of process layout : | ||
| (A) Reduced material handling. (B) Less capital investment. (C) Smooth flow of materials. (D) Less floor area occupied by the material in transit and for temporary storages. |
|||
|
d.
|
The following is not the principle of material handling : | ||
| (A) Reduce the handling of material. (B) Use unit loads. (C) Move materials at high speeds. (D) Use handling equipment below its capacity. |
|||
|
e.
|
In a PERT model an activity has the following time estimates
: Pessimistic time = 16 days. Most likely time = 8 days. Optimistic time = 4 days. The expected time estimate to carry out the activity is |
||
| (A) |
(B) |
||
| (C) |
(D) |
||
|
1
|
|||